Lucan Swimming Pool Progress Report 27/02/2018 Motion
September 24, 2023
MEETING OF LUCAN AREA COMMITTEE
Tuesday, February 27, 2018
MOTION NO. 7
MOTION: Councillor L. O’Toole
“That this Committee requests the Chief Executive provide an update on the Lucan Swimming Pool and to advise that all plans are still within the projected time frame.”
REPORT:
The Fire Safety Officer in Dublin City granted the Fire Safety Certificate on the 15/2/18.
A progress report is now to be submitted to the DTTaS and it is estimated that the tender date will be towards the end of March.
The tender process will take six weeks to complete.
On conclusion of the tender process a Tender Report will be prepared and issued to the Department of Transport Tourism and Sport for final approval.
Once this approval is received the Contractor will be appointed and work will begin. This start date is dependent on the Departments approval but is estimated at June/July 2018.
The project will take 12 – 18months to complete and fit out ready for operation by the end of 2019.